These guidelines have been developed to aid in the preparation of
construction and material specifications for a specific project. These guidelines should
be modified to:
| 3.1 |
ACCEPTANCE OF UNITS ON SITE |
| 3.1-1 |
All units shall be subject to final acceptance on site. Where the
contract includes the construction of the wall, it shall be the Contractors
responsibility to ensure that all units are erected in an undamaged condition. |
| 3.1-2 |
The Project Engineers representative may carry out such tests
or measurements as deemed necessary to be satisfied that the units delivered to the site
are equal in quality to the approved specification and design. Where the tests are of a
destructive nature and the units prove acceptable, the cost of the units as delivered to
the site of testing will be charged to the contract. |
| 3.1-3 |
Units which do not satisfy the material requirements of the
dimensions and tolerances of this specification will be liable to rejection. |
| 3.1-4 |
Units with cracks or other imperfections which, in the opinion of
the Project Engineer, are unacceptable shall not be placed in the wall. |
| 3.1-5 |
Rejected units shall be removed from the site and shall be replaced
with acceptable units at no extra cost to the contract. |
| 3.2 |
WALL LAYOUT |
| 3.2-1 |
Amastone Retaining Wall construction shall be in reasonably close
conformity to the lines, grades, design and dimensions shown on the plans and as
established by the Project Engineer by means of surveyed staking. |
| 3.2-2 |
The Contractor shall obtain the Project Engineers approval of
wall alignment before placing granular bedding, concrete leveling pad or placing any
Amastone units. |
| 3.3 |
EXCAVATION |
| 3.3-1 |
A bench excavation to sound material shall be made for the base of
the wall. Unless shown otherwise on the project plans, the benches shall be horizontal in
the line of the wall. The depth of the excavation shall be a minimum of 1.0 feet below the
proposed finished ground level at the front face of the wall, or as shown on the project
plans. |
| 3.3-2 |
Contractor shall call for and obtain the Soils Engineers
inspection and approval of the excavated foundation prior to casting any concrete or
placing any Amastone units. |
| 3.3-3 |
Finished base excavation to within 0.5 inches of the base elevation
and shall include vertical steps in 8" increments where plans indicate base of wall
is to step. |
| 3.4 |
GRANULAR BEDDING |
| 3.4-1 |
Unless specified by the Project Engineer or project plans, a
concrete leveling pad is not required. |
| 3.4-2 |
After verification by the Soils Engineer of base soil adequacy, a
granular bed may be utilized below the base course of Amastone units. Before placement of
the granular bedding, It is recommended that the base soil be compacted to a minimum 95
percent of Standard Proctor. It is recommended that a minimum of 4 inches of 3/4 inch
crushed rock be used for the granular bedding. The wall is initiated by placing the first
course of Amastone units directly onto granular bedding. |
| 3.4-3 |
It is essential that the granular bedding be protected. Ensure that
the Amastone retaining wall is buried at least 1.0 feet below the proposed finished ground
level at the front face of the wall, or as directed by the project engineer. |
| 3.5 |
CONCRETE LEVELING PAD |
| 3.5-1 |
For portions of the wall where the bearing pressures exceed 2,500
psf, a cast-in-place concrete leveling pad with a minimum thickness of 3 1/2 inches and a
minimum width of 24 inches may be constructed. This pad shall be placed so that the wall
is constructed centrally to the pad. The leveling pad may require rebar or fiber mesh
reinforcement for higher walls that exert bearing pressures greater than 4,000 psf.
Concrete leveling pads shall be manufactured and placed in accordance with ASTMC and shall
have a minimum compressive strength of 3,000 psi at 28 days. |
| 3.6 |
AMASTONE BLOCK PLACEMENT |
| 3.6-1 |
The units shall be handled and placed in such a manner that they
are not cracked or chipped and so that no damage is caused to the seating areas. |
| 3.6-2 |
The first course of units shall be placed side by side on the
granular bedding (3/4" crushed rock) or concrete leveling pad. Care shall be taken in
the placement to ensure firm bedding against the base. |
| 3.6-3 |
The units in the base course shall be checked for level and
alignment. |
| 3.6-4 |
The units shall be placed in a uniform pattern as shown on the
drawings or as approved by the Project Engineer. |
| 3.6-5 |
Where required by project plans, steel rebar may be placed in the
dowel notch at the back of the Amastone units in such a way that the steel spans three
blocks and that the geosynthetic reinforcement interlocks with the steel rebar. The steel
shall be #4, grade 40 rebar and a minimum of 24 inches in length. |
| 3.6-6 |
When capstones are used on the top course of the wall, they shall
be epoxied in place on a clean, dry surface. |
| 3.7 |
GEOSYNTHETIC REINFORCEMENT |
| 3.7-1 |
Geosynthetic Reinforcement shall be the type shown on the drawings
or that which conforms to a structural stability analysis design for a specific project. |
| 3.7-2 |
If required, the geosynthetic reinforcement manufacturer shall
provide certification that the selected reinforcement meets the design requirements of the
projects retaining wall stability calculations. |
| 3.7-3 |
Geosynthetic reinforcement shall be laid horizontally on compacted
fill at the specified elevations and patterns shown on the construction drawings or the
structural stability analysis. Proper orientation of the geosynthetic reinforcement shall
be verified by the contractor. |
| 3.8 |
BACKFILL MATERIALS |
| 3-8.1 |
BACKFILL BEHIND WALL Backfill material
used behind the wall shall conform to structural stability calculations. |
| 3.9 |
FILL PLACEMENT IN UNITS |
| 3.9-1 |
Backfill materials within the wall shall be placed in layers
corresponding to the height of the blocks. It is recommended that fill within units be
comprised of 3/4" crushed rock. Insure that each course is completely filled prior to
proceeding to the next course. Material immediately behind the block should be compacted
using only hand-operated compaction machinery. |
| 3.9-2 |
Concrete grout can be used to fill the Amastone units if required
by the plans or Project Engineer. Concrete grout may be placed with or without steel
reinforcement as per the plans. No more than three courses should be grouted per pour.
Care should be taken not to alter the block alignment during grouting. |
| 3.10 |
FILL PLACEMENT FOR GEOSYNTHETIC REINFORCEMENT |
| 3.10-1 |
Fill placed in areas reinforced with geosynthetic reinforcement
shall be placed in 12 inch lifts and compacted to 90 - 95 percent of standard proctor.
Care should be taken not to disturb the alignment of the units during backfilling and
compaction operations. |
| 3.10-2 |
Backfill shall be placed from the block backwards to insure
tautness, and shall be placed in such a manner as to minimize both the development of
wrinkles in the reinforcement and the movement of the reinforcement. |
| 3.10-3 |
Only hand operated compaction equipment shall be allowed within 3
feet of the wall face. Special care should be taken when operating heavy equipment on fill
over the geosynthetic reinforcement. No equipment shall be operated directly on the
reinforcement. |
| 3.10-4 |
Compaction tests should be measured no less than 24 inches from the
back of the block. |